03.31.10
The Work Continues
As Team 3 left the work site, here are the latest pictures.

The water treating system is finished and
David sampled the water and lived.

The septic tank including the new drain field is finished.
Debi and her crew got the garden/atrium cleaned and ready for plants. She also got the front yard cleaned and used the scrap concrete to pave the driveway. In addition, they cleared an area for the kitchen garden. The electrical room to house the generator and batteries is almost finished.
The doors and windows are finished.

The kitchen countertops are almost done, the tile in the bathroom including the counter tops is almost finished, the painting of the interior is almost finished.


In spite of all the almosts, the orphanage is beginning to look like a house.